April 23, 2015- Boynton Beach Utilities Ion Exchange Project Groundbreaking, 9:00 AM

Updated Project Schedule and Milestone 9/30/15

Contract Effective Date Wednesday, July 02, 2014

Phase 1 Notice To Proceed
Thursday, July 10, 2014
Date of Commencement (NTP+5) Monday, July 14, 2014
Review Of Alternative Design/Value Engineering Wednesday, August 06, 2014
Design Definition Meeting Wednesday, August 20, 2014
Design Development Documents Sunday, January 11, 2015
Submit Permitting Applications and Documents Sunday, January 11, 2015
Negotiate / Finalize GMP Friday, February 13, 2015
March Board Meeting Monday, March 2, 2015
Preconstruction Meeting Thursday, March 11, 2015
Issue Owner Contract Monday, March 11, 2015
Provide Bonds/Insurance Friday, March 19, 2015
Execute Owner Agreement Monday, March 31, 2015

Phase 2 Notice To Proceed
Tuesday, April 7, 2015
Date of Commencement (NTP+5)* Saturday, April 11, 2015
Early Substantial Completion Bonus Date* Monday, August 1, 2016
Substantial Completion* Monday, August 22, 2016
Punchlist/Closeout* Saturday, November 19, 2016
Project Final Completion (SC +90)* Saturday, November 19, 2016
Warranty (2 Years from Final)* Sunday, November 18, 2018